traffic control
The project included the construction of three new mainline 13.8 kV circuits on the City’s distribution system to increase capacity and reliability. The circuits were built in underground fashion; two extending from the City’s substation near the airport to the downtown area, and one extending from the City’s substation near the airport to the event center. DGR services for this project included the initial study work, project development, engineering design, permitting, construction administration, and resident construction observation.