Rock Riffle Dam

June 3, 2024

Witnessing the sharp decline in Regional’s wellfield capacity during 2020 and 2021, Regional and DGR Engineering (DGR) began conversations in 2021 with the intent of shoring up Regional’s wellfield capacity.

The principle behind a riffle dam structure is that the water in the river channel and water in the adjacent aquifer are hydraulically connected. Raising the level of the river raises the water level in the aquifer, giving wells more available drawdown to pump more water. The correlation between the river and the aquifer levels is dependent on the geologic conditions of the aquifer. DGR helped Regional secure the services of LRE Water, a hydrogeology firm which used previously-collected geologic records to set up a model, which confirmed that the aquifer and the river had a strong hydraulic connection.

Obtaining permits from the DNR to build the riffle dam required significant effort. Notably, the river programs and fisheries divisions were concerned respectively about impedance to recreational paddlecraft and fish passage. It was important that the structure was designed with a deep, center channel to allow navigation of the river. DGR used HEC-RAS river modeling to simulate multiple iterations of dam heights to determine the maximum height that could be used. Through the modeling and permitting process, a structure height was settled on to raise the upstream river level 2.83 feet.

The structure has netted Regional an approximately 100 GPM in additional wellfield capacity. This may not seem like much, but it makes a big difference in helping Regional meet its customers’ water needs. Perhaps more importantly, it helped stop the drought-induced aquifer decline and it buys Regional time as they and DGR pursue additional water supply solutions.

Low Head Dam Design & Survey

September 28, 2018

DGR Engineering performed the topographic survey as well as the design of the low head dam.  Construction of the dam involved removing an existing dysfunctional dam and installing sheet piles and rip rap.  After construction, the water table rose, benefiting the City’s well fields, and the water quality improved downstream.