Keystone Transmission Line

October 4, 2018

The  project included full services for 58 miles of new 115 kV line and 5 miles of new 69 kV line.  There were four separate transmission line segments making up the project, each in a different location within the state.

DGR services for this project included permitting, right-of-way acquisition, surveying, design, construction administration, construction staking, and resident project observation.