DGR Engineering Welcomes Derek Lee

November 9, 2018

Site Development

November 5, 2018

DGR performed the boundary and topographic surveying as well as the site design of school building addition as a subconsultant of Architecture, Inc.
The school facility addition design included storm sewer upgrades, pedestrian facilities to multiple building levels, enhanced and expanded parking, as well as significant embankment work to match the existing site constraints.

The addition cut off an existing overflow drainage path so an enhanced storm sewer system capable of draining runoff from a 500 year storm event was designed and constructed.

This project required working with a building design team and ownership group to overcome design challenges and communicate with all project stakeholders.  The facility was completed and opened in late fall of 2015 for the Central Lyon Community School District.

Water Main Replacement

October 5, 2018

This project consisted of water main replacement on St. Paul Avenue from Benson Road to 39th Street North in Sioux Falls, South Dakota.  Work included water main replacement, sanitary manhole repair, replacement of surfacing over trenches, and boulevard restoration.  The water main replacement successfully utilized both open trenching and directional drilling methods.  Sanitary manhole repair included reconstructing manhole benches and inverts along with installing manhole external frame seals.

Water Main Extension

October 5, 2018

This project consisted of installing 8” water main beginning approximately 1,700 feet southwest of the Great Bear entrance road and continuing 3,700 feet to the northeast.  This project included water main installation, asphalt removal and replacement, and site restoration and grading.  Also included in this project was the grading and paving for a turn lane approximately 600 feet long on Rice Street for the proposed TJN site.

Water Main Development

October 5, 2018

This project consisted of installing approximately 4,500 feet of 16” DIP water transmission main on Six Mile Road between 10th Street and 26th Street in Sioux Falls, SD.  This work included water main installation, directional boring 24” steel casing across SD Highway 42 and under a large box culvert, pavement replacement, and restoration.