DGR Engineering (DGR) and the Town of Chancellor worked together to plan an infrastructure improvements project. Ultimately, solutions were divided into three project phases. Phase 1 included Main Street and the west half of the community. The Town of Chancellor received funding which included nearly 89% in grants and principal loan forgiveness.
Phase 1 included the beginning of a new storm sewer system. DGR and the Town worked with landowners to acquire the needed land and easements for a new storm sewer outlet. It allowed the storm sewer to be extended across the southern end of town in each of the phases of construction, connecting each of the street’s drainage to a larger diameter storm pipe to improve drainage.
Chancellor was awarded Clean Water and Drinking Water State Revolving Funds for their planned Phase 2 project, which covered the central part of the community. They followed with funding for their Phase 3 project and were successful in securing approximately 85% grant and principal loan forgiveness for both Phase 2 and Phase 3 projects.
Each of the project phases included the replacement of sanitary sewer main and services with PVC pipe, replacement of all sanitary manholes with new concrete manholes, replacement and up-sizing of PVC pipe water main and water services as well as adding additional water services to areas that previously did not have existing water main. New street surfacing was placed after the underground improvements. While Main Street included concrete surfacing on the north two blocks, the remaining streets will maintain a rural section paved with asphalt surfacing. The rural section is designed with minor ditches graded along the roadways and culvert replacement at the driveways and intersections to allow the stormwater to flow to the storm sewer system, located at the southern portions of the streets, to reduce the stormwater ponding that had occurred.
The infrastructure investment will significantly improve and benefit the community and all residents. They are looking forward to project completion and many years ahead with reliable infrastructure to support their Town.
Our Chancellor, SD Phase I Infrastructure Improvements Project
received a Concrete Award of Excellence. It was awarded through
the South Dakota Ready Mix Concrete Association at the
ACPA/SDRMCA Annual Conference in Deadwood recently.
Co-recipients included: Town of Chancellor, First Rate Excavate,
Big Al’s Contracting and Ace Ready Mix.
Representing DGR were Aaron Miller and Andrew Wolters.