Subscribe to our Newsletter

Categories

ADA accessibility

Street and Utility Improvements

June 3, 2024

Poor drainage was causing accelerated deterioration along Hawarden’s Avenue L, which serves as the primary collector route to the town’s nursing facilities and the local hospital. When repeat efforts to patch and repair this critical stretch of roadway were only fleetingly effective, the City of Hawarden partnered with DGR Engineering to develop a comprehensive approach for improving Avenue L for the long-term benefit of the community.

The improvements included installing a new storm sewer system, making repairs to the existing water main and sanitary sewer, and taking steps to improve future drainage, all before installing new 6” concrete pavement.

Athletic Field Site Design

April 8, 2024

Project planning by Augustana University and DGR Engineering to upgrade Bowden Field to a championship level began in 2018, and eventually culminated in a new facility which opened for the 2023 season.

The biggest challenge: fitting a new modern facility within the existing field’s footprint (circa 1991). To achieve this, home plate was shifted approximately 12 feet south to maintain existing fencing dimensions and provide room for chair back seating and a fan suite/press box behind home plate. Also, an extended planning process was necessary to balance donation momentum with the university’s facility expectations for a championship-level facility.

The final project plan balanced design goals with the funding while utilizing bid alternates for several features to allow the University flexibility in decision-making in the following areas:

• Lighting
• Outfield padding
• Dugout Cabinets
• Press box lift
• Home team dugout kitchenette
• Chairback seating – Potential future addition space

The final result is a state-of-the-art facility that all parties can be proud of and that will serve the needs of Augustana University’s softball team and its fans for many years.

Recreational Trail

October 5, 2018

This project consisted of one and a half miles of 8’ wide recreational trail along the Big Sioux River and in the City Park in Dell Rapids, South Dakota.  Also included in this project was a 100’ pedestrian bridge across the Dells of the Big Sioux River and a river access concrete pad in conjunction with the recreational improvements.  Recreational trail paving was with 4” concrete and was made ADA accessible.

Utility & Street Improvements

October 5, 2018

This project consisted of approximately 2,200 feet of 6” and 8” water main replacement along with 1,400 feet of 8” sewer replacement.  Also included with this project were street drainage improvements as well as the installation of ADA sidewalk ramps at 11th Street and Garfield Avenue.

River Crossing/Street Improvements

October 5, 2018

This project consisted of 4,200 L.F. of street improvements on 15th Street (Clark Avenue to Garfield Avenue), Garfield Avenue (15th Street to 12th Street), and State Avenue (Thresher Drive to 12th Street).  Also included in this project were 4,400 feet of water main, 2,000 feet of sanitary sewer, and two directionally drilled river crossings approximately 350 feet each.  Street paving on 15th Street and Garfield Avenue was with 9″ concrete, with asphalt concrete paving used on State Avenue and at intersecting street tie-ins. ADA accessible sidewalks were also installed on this project for safe access to the middle school and high school.