Subscribe to our Newsletter

Categories

Treatment Facilities

Treatment Plant & Well Exploration

July 29, 2021

Treatment Plant & Well Exploration

Photo Sep 13, 3 08 59 PMedit

Water System Improvements
add capacity on existing site

Osceola County Rural Water System Constructs
Treatment Plant and Adds Ground Storage Reservoir

Project Owner:
Osceola County Rural Water System

Key Experience:

  • Maintaining the use of existing facilities during the construction of the new water treatment plant on the same site
  • Surface resistivity aquifer testing to efficiently pinpoint high capacity wells

Key Features:

  • 2,400 gpm water treatment plant for iron and manganese removal
  • 1 million-gallon glass-fused steel ground storage reservoir
  • 750 kW standby generator

Osceola County Rural Water System (OCRWS) provides service to 3,200 customers in five counties of Northwest Iowa. OCRWS continues to see increasing water demands from ag and confinement livestock facilities, industrial users and municipalities. OCRWS maintains two water treatment plants that serve the North Phase and South Phase of the rural water system. During 2017, OCRWS experienced water demands that exceeded their South Phase Water Treatment Plant (WTP) capacity, which confirmed the need to move forward with expansion of the facility.

The existing South Phase WTP was constructed in the early 1980’s, with a self-contained aeration/detention/filtration system called an Aerelator®. The existing treatment equipment had reached the end of its useful life, and there was no way to rehab the existing equipment while maintaining treatment for the South Phase. Additionally, the existing WTP capacity was unable to meet OCRWS’s growing water demands, so OCRWS decided to construct a new South Phase WTP.

DGR Engineering (DGR) worked closely with OCRWS to design a new WTP to target iron and manganese removal from shallow groundwater source near the site. The new WTP was designed on the existing WTP site to minimize the project footprint and avoid additional land purchase. With the WTP location being highly visible just off IA Hwy. 10, OCRWS and DGR worked together to develop a design that not only met their water quality and capacity needs, but was also aesthetically pleasing. The new treatment process includes aeration, detention, and filtration using a gravity filter arrangement, and will increase OCRWS’s treatment capacity from 750 gpm to 2,400 gpm.

IMG_2846
20180515_123022

OCRWS also needed additional source water capacity to utilize the treatment capacity of the new WTP. DGR used a surface resistivity testing program to generate multiple snapshots of the aquifer depth and production capacity. Resistivity testing uses a line of electrical probes to quickly estimate soil characteristics, without the time and expense of test drilling. The testing provides a series of graphs like the one shown below. It allowed OCRWS to gather aquifer information on hundreds of acres of potential well sites with 3 days of field work and quickly identify the highest probability areas for high capacity wells. The results of the graphs were verified with test drilling, and two new well sites were identified in the thickest and most productive areas of the aquifer.

Increasing demands at the new WTP made additional on-site storage necessary. A 1 million-gallon glass-fused steel ground storage reservoir was constructed to accommodate these needs. The additional finished water storage on-site will also give OCRWS flexibility in how they choose to operate the facility.

The total construction cost of the new WTP project was $7.8 million, which was financed using a combination of Iowa State Revolving Fund (SRF) loan and private funding. The SRF funding package included a forgivable SRF loan for standby power generation. DGR also helped OCRWS navigate SRF’s American Iron and Steel requirements. The new improvements to South Phase water source will allow OCRWS to meet current and future water demands while providing their customers with reliable, high quality water.

DCIM100MEDIADJI_0025.JPG

Water System Expansion

May 4, 2021

Water System Expansion

20180607_151039 skyedit

Water system expansion project
adds customers and improves system

Kingbrook Rural Water, Inc. Implements Long-Range Plan by
Improving System Performance and Serving New Customers

Project Owner:
Kingbrook Rural Water, Inc.

Key Experience:

  • Completion of a long-range plan spanning several decades and multiple projects to interconnect water sources
  • Optimized treatment plant performance by moving chemical injection points and adding finished water storage
  • Large rural water pipeline project that extends service to new members and improves system capacity

Key Features:

  • USDA Rural Development funding, including grant and low-interest loan, saving client over $4 million in interest payments
  • 215 miles of pipe 1½” to 16” in diameter extending service to 260 new customers
  • New 630,000-gallon bolted steel storage tank

Kingbrook Rural Water, Inc. is a regional water provider in eastern South Dakota, serving approximately 4,950 residential, livestock, and commercial users in more than 11 counties. They serve customers from three different water treatment plants located approximately 50 miles from each other. The treatment plants are located in rural areas near the small towns of Bruce, De Smet and Chester, SD. The original system construction happened in the late 70’s and early 80’s. All three treatment plants were expanded in the 90’s and early 2000’s to meet their growing needs.

In the mid-2000’s, DGR Engineering (DGR) and Kingbrook began developing a long-range plan to interconnect their three treatment plants with large diameter transmission mains. The goal of the plan was to provide another level of backup at each treatment plant in case of an emergency. This emergency planning was in addition to the typical approach for systems to have standby generation, backup pumps, etc. Another goal of the plan was to provide operational flexibility by having two sources that could serve any of their subsystems. Each year, an annual planning event is held to review system operations, new growth trends, and changes in existing customer demands. The plan is updated and modified to meet the current and future needs of the system.

Approximately every four to five years, these plans are combined into a project that not only improves the system for existing customers, but also extends rural water service to new customers. Conducting systematic expansion projects results in regular improvement of the system. It also allows the utility to make the most efficient investments in their system by taking advantage of low-interest loans, grants, and economies of scale when bidding out multiple improvements and new connections as one large project. In the past 15 years, Kingbrook has installed about 50 miles of transmission mains between their treatment plants, but still needed about 25 miles between Bruce and De Smet to complete the long-range planning goal of connecting their water treatment plants.

20180405_155622
20180608_180811
IMG_1210

Kingbrook began planning their current expansion project in 2015. Tremendous demand for new service connections made this expansion project the largest expansion project ever undertaken by Kingbrook. Much of the additional water demand was located within the De Smet plant service area that couldn’t be met with the existing system’s transmission capacity. Previous projects had increased elevated storage capability in the De Smet plant service area and connected with the Chester plant. But more capacity was needed to serve the new customers.

Our Approach
DGR began by helping Kingbrook optimize the De Smet treatment plant. Highly variable iron concentrations from their north well field made chemical dosing problematic. Kingbrook optimized the treatment efficiency of the plant by changing oxidants and moving the chemical dosing locations. These changes extended the filter runtime, reduced the overall chemical requirements of the plant, and increased production capacity.

Next, the existing storage capacity at the De Smet treatment plant only had about three and a half hours of peak demand storage, which made plant operation difficult. Kingbrook selected a two-phase process to build one 630,000-gallon tank now, which will increase on-site storage to about eight hours, and build a second tank as part of a future project, when demand increases.

Finally, DGR designed pipeline that would serve the new customers and complete the interconnection to Kingbrook’s third water source near Bruce. When complete, this project will add approximately 190 miles of pipe for system improvements and new services, as well as approximately 25 miles of 12, 14, and
16-inch diameter pipeline to interconnect the Bruce plant with
the De Smet plant.

The project is was finished in the summer of 2019. This project
not only meets the needs of new customers who signed up on
this expansion project, but it also achieved a major milestone
of Kingbrook’s long-range planning – the interconnection of
their water sources to improve system reliability and flexibility
of operations.

Water Treatment Plant

October 12, 2018

The rural residents around North Sioux City and Elk Point South Dakota can find as much water as they want, just by sinking a well anywhere in the Missouri River Alluvial Valley.  The problem is that the “good water” in this area, which is lower in iron and manganese, is laced with radium.  Rural communities like Wynstone and Sandy Meade were faced with the challenge of Radium removal to protect their customers.

Clay Rural Water System partnered with these developments and the surrounding rural customers to bring Radium Free water to over 500 homes.  These residents dealt with contaminated drinking water for decades, and now have confidence in the water they are drinking. DGR Engineering worked with Clay Rural Water System to construct a reverse osmosis water treatment plant to take water with raw water combined radium 226 + 228 of 12.4 pCi/L down to below detection limits of <1.0 pCi/L.   These customers have been receiving this safe drinking water now for over a decade.

The plant treats the deep well water directly with reverse osmosis without pre-treatment, even though the raw water has high iron and manganese levels.  This innovative treatment approach saved significant construction and operational costs for the water system.

Ground Storage Reservoir

October 12, 2018

Construction of a bolted steel glass lined tank, foundations, and miscellaneous appurtenant work.  Nominal size is 300,000 gallons, 36′ diameter, 38′ high.

The ground storage reservoir is a critical component of the water treatment process, allowing flow equalization between the filtration process and the softening system.

Water Treatment Plant Expansion

June 21, 2018

The City of Estherville operates an iron and manganese removal and zeolite softening facility. The plant had adequate softening capacity for growth, but had exceeded the rapid sand filtration capacity of the facility. The expansion was rated at 1,200 gpm and included the following work:

Construction of a water treatment plant expansion of 1200 gpm capacity, including concrete gravity filter cells, masonry building, yard and process piping, line shaft turbine high service and backwash pumps, horizontal split case transfer pumps, HVAC, electrical and control, site work and miscellaneous appurtenant work.