Client:
City of Redwood Falls

Redwood Falls, MN

Key Features:

  • Replacement of old overhead infrastructure with new underground infrastructure,
    to increase reliability and improve aesthetics
  • Eliminated public safety concern of old transformer platform structures

Key Experience:

  • Responsibility and involvement throughout the project, from initial planning and design
    to construction administration and contract closeout
  • Development of a multi-year plan for staged construction of the improvements
  • Coordination with private communications utilities including joint use of excavations

Distribution Conversion

Electric distribution lines in the downtown alleys of Redwood Falls, MN consisted of large overhead structures which included transformers mounted on platforms. Due to concerns with the age and condition of the structures, along with safety clearances to energized equipment and conductors, a project was undertaken to replace the old infrastructure with new underground lines and associated padmount equipment. In addition, these improvements would improve the overall attractiveness of the area.

The 11 block project was split into two phases to allow for completion over two construction seasons. In addition to burying the overhead primary circuitry, most of the overhead secondary circuitry associated with the conversion area was converted to underground.

DGR Engineering developed a full design for the new underground circuitry, including equipment and cable sizing, equipment locations, line routes, and material lists. Bidding and contract documents for construction of the improvements were developed, which included detailed design drawings, staking sheets, and technical specifications. The completed project resulted in a safer and more aesthetically pleasing downtown area that was also up to current standards for infrastructure and reliability.

Featured Projects

All
  • All
  • Aviation
  • Civil
  • Electrical Power
  • Survey
  • Wastewater
  • Water

Floodplain Analysis

DGR employed a Geographic Information System (GIS) in conjunction with the U.S. Army Corps of Engineers to first determine the 100-year flood elevations and delineate the floodway boundaries.

Floodplain Analysis
Sutherland, IA

Distribution Conversion

Due to concerns with the age and condition of the structures, along with safety clearances to energized equipment and conductors, a project was undertaken to replace the old infrastructure with new underground lines and associated padmount equipment.

Distribution Conversion
Redwood Falls, MN

Street & Utility Improvements

Morningside Avenue was reconstructed totaling approximately 1,300 linear feet. The project included new sanitary sewer, water main, storm sewer, fiber conduits, decorative street lighting, and 9-inch concrete paving with colored concrete sidewalks.

Street & Utility Improvements
Sioux City, IA

Wastewater Treatment Facility (SBR)

The City ultimately determined a flow-through style SBR system to be the preferred choice based on the selection criteria and the ability to meet anticipated permit limits.

Wastewater Treatment Facility (SBR)
Orange City, IA

Site Development

Planning started with site plan design for the new facility to offer maximum exposure to traffic on Highway 75.

Site Development
Rock Rapids, IA

Wastewater Treatment Facility (SBR)

The new plant, rated for 5.3 million gallons per day (MGD) peak day, doubles the capacity of its predecessor.

Wastewater Treatment Facility (SBR)
Sheldon, IA