Client:
Stanhope Municipal Utilities

Stanhope, IA

Key Features:

  • Construction of a new 69-12.47 kV Substation
  • Delta to Wye distribution system conversion
  • Detailed financial modeling of alternatives
  • Electric retail rate development

Key Experience:

  • Responsibility and involvement in all phases of the project, from project feasibility to final testing and checkout
  • High-level of coordination among multiple entities

New Substation Construction

After careful consideration of the alternatives and rate impacts on its customer base, Stanhope Municipal Utilities (SMU) approved proceeding with the construction of its own substation and “wye-ing out” its distribution system.

Following the decision, a full cost-of-service rate study was completed for SMU’s customers. This study also allocated the costs of providing service to the proposed rate classes, with the goal of having each rate class pay its fair share of the costs of operating the electric system (including covering its share of the cost of the proposed facilities). The proposed rate changes were adopted, which led to SMU successfully issuing electric revenue bonds, with an overall interest rate averaging less than 3%, covering maturities of up to 20 years.

The project construction process involved a high level of coordination among many parties. Public bidding processes were used to acquire major materials and contractors to build the new substation and convert the distribution system. Webster City Municipal Utilities (SMU’s electric system operations & maintenance provider) directed much of the complicated process of cutting over to the new facilities, aided by DGR engineers and field technicians.

Not only was the project completed in time to coordinate with the regional transmission system voltage upgrade, but the overall cost of the project was significantly under the original project estimate. Costs were reduced due to some of the unique ways the materials acquisition and construction processes were executed.

Funds for the work were obtained at reasonable long-term cost to SMU, and the new retail rates necessary to support the debt service were implemented. Overall, DGR was able to assist SMU in all aspects of the project, from initial evaluation, to design and financing, through final construction.

Featured Projects

All
  • All
  • Aviation
  • Civil
  • Electrical Power
  • Survey
  • Wastewater
  • Water

Street & Utility Improvements

Morningside Avenue was reconstructed totaling approximately 1,300 linear feet. The project included new sanitary sewer, water main, storm sewer, fiber conduits, decorative street lighting, and 9-inch concrete paving with colored concrete sidewalks.

Street & Utility Improvements
Sioux City, IA

Wastewater Treatment Facility (SBR)

The City ultimately determined a flow-through style SBR system to be the preferred choice based on the selection criteria and the ability to meet anticipated permit limits.

Wastewater Treatment Facility (SBR)
Orange City, IA

Site Development

Planning started with site plan design for the new facility to offer maximum exposure to traffic on Highway 75.

Site Development
Rock Rapids, IA

Wastewater Treatment Facility (SBR)

The new plant, rated for 5.3 million gallons per day (MGD) peak day, doubles the capacity of its predecessor.

Wastewater Treatment Facility (SBR)
Sheldon, IA

Lift Station, Control Panel and Valve Vault

The SE Sanitary Sewer Extension project provided sanitary sewer service to a previously un-serviced area southeast of Dell Rapids, SD.

Lift Station, Control Panel and Valve Vault
Dell Rapids, SD

Wastewater Treatment Facility (SBR)

The new SBR system utilizes the existing aeration lagoon for equalization and another lagoon cell for sludge storage, which reduced the cost of the project for the City and provided more operational flexibility.

Wastewater Treatment Facility (SBR)
Dell Rapids, SD