Client:
City of Sioux Falls
Sioux Falls, SD
Key Features:
- 8” water main distribution
- Turn lane addition to TJN Enterprises on East Rice Street
Key Experience:
- Coordination/cooperation with the Sioux Falls Parks Department and Xcel Energy
- Coordination with railroad for water main installation and access coordination
Water Main Extension
This project consisted of installing 8” water main beginning approximately 1,700 feet southwest of the Great Bear entrance road and continuing 3,700 feet to the northeast. This project included water main installation, asphalt removal and replacement, and site restoration and grading. Also included in this project was the grading and paving for a turn lane approximately 600 feet long on Rice Street for the proposed TJN site.
Featured Projects
- All
- Aviation
- Civil
- Electrical Power
- Survey
- Wastewater
- Water
New Water Treatment Plant
New Water Treatment Plant delivers higher quality and more economical water.
Osgood, IA
New Water Distribution System
The City’s residents enjoy high quality water that comes to them in a new and reliable distribution system.
Revere, MN
Site Development, Utility Improvements
A multi-phase plan for infrastructure projects was developed for the City of Alton.
Alton, IA
Neighborhood Reconstruction
Health, safety and public welfare were all improved by this project.
Brandon, SD