Client:
East River Electric Cooperative

Madison, SD

Key Features:

  • Total line length of 63.0 miles
  • 115 kV and 69 kV, horizontal line post, single pole construction
  • DGR service for this project included route selection assistance, state permitting, right-of-way acquisition, surveying, design, construction staking, construction management, and resident construction observation.

Key Experience:

  • Performing the right-of-way acquisition for the entire project route.
  • Working with the Owner to finalize and adjust routing as necessary during design.
  • Working with the Owner’s set of design and procurement standards to insure these lines were constructed similarly to their other transmission lines on their system.

Keystone Transmission Line

The  project included full services for a 58 miles of new 115 kV line and 5 miles of new 69 kV line.  There were four separate transmission line segments making up the project, each in a different location within the state.

DGR services for this project included permitting, right-of-way acquisition, surveying, design, construction administration, construction staking, and resident project observation.

Featured Projects

All
  • All
  • Aviation
  • Civil
  • Electrical Power
  • Survey
  • Wastewater
  • Water

Floodplain Analysis

DGR employed a Geographic Information System (GIS) in conjunction with the U.S. Army Corps of Engineers to first determine the 100-year flood elevations and delineate the floodway boundaries.

Floodplain Analysis
Sutherland, IA

Distribution Conversion

Due to concerns with the age and condition of the structures, along with safety clearances to energized equipment and conductors, a project was undertaken to replace the old infrastructure with new underground lines and associated padmount equipment.

Distribution Conversion
Redwood Falls, MN

Street & Utility Improvements

Morningside Avenue was reconstructed totaling approximately 1,300 linear feet. The project included new sanitary sewer, water main, storm sewer, fiber conduits, decorative street lighting, and 9-inch concrete paving with colored concrete sidewalks.

Street & Utility Improvements
Sioux City, IA

Wastewater Treatment Facility (SBR)

The City ultimately determined a flow-through style SBR system to be the preferred choice based on the selection criteria and the ability to meet anticipated permit limits.

Wastewater Treatment Facility (SBR)
Orange City, IA

Site Development

Planning started with site plan design for the new facility to offer maximum exposure to traffic on Highway 75.

Site Development
Rock Rapids, IA

Wastewater Treatment Facility (SBR)

The new plant, rated for 5.3 million gallons per day (MGD) peak day, doubles the capacity of its predecessor.

Wastewater Treatment Facility (SBR)
Sheldon, IA