Client:
West River Lyman-Jones Rural Water Systam
Murdo, SD
Key Features:
- 70 total miles of pipeline, including Phase 2 and 3
- Two stream crossings over 500 ft in length
Key Experience:
- Trenchless technologies used to minimize fish and wildlife disturbance
Pipeline Construction
Construction of the North Core Pipeline project consisted of approximately 70 miles of pipeline from near Ft. Pierre to Philip, four ground storage reservoirs, and four pump stations. The project included 12-inch through 16-inch diameter pipe, valves, stream crossings, and miscellaneous appurtenant work. The pipeline route followed the route of Highways 14/34 with some cross-country segments. Stream crossings were installed using a directional boring method as to avoid disturbance to fish and wildlife. The pipeline system was designed for over 1,700 gpm and brought water service to rural customers and small communities in western South Dakota.
Featured Projects
- All
- Aviation
- Civil
- Electrical Power
- Survey
- Wastewater
- Water
Upgrading Communications
DGR engineers helped L&O Power Cooperative improve communications on its electric transmission system using existing transmission lines, fiber and underground fiber line.
Rock Rapids, IA
Treatment Plant & Well Exploration
DGR Engineering worked closely with OCRWS to design a new Water Treatment Plant to target iron and manganese removal from a shallow groundwater source near the site.
Northwest IA
Distribution Conversion
Due to concerns with the age and condition of the structures, along with safety clearances to energized equipment and conductors, a project was undertaken to replace the old infrastructure with new underground lines and associated padmount equipment.
Redwood Falls, MN
Street & Utility Improvements
Morningside Avenue was reconstructed totaling approximately 1,300 linear feet. The project included new sanitary sewer, water main, storm sewer, fiber conduits, decorative street lighting, and 9-inch concrete paving with colored concrete sidewalks.
Sioux City, IA
Wastewater Treatment Facility
The new plant, rated for 5.3 million gallons per day (MGD) peak day, doubles the capacity of its predecessor.
Sheldon, IA
Site Development
Planning started with site plan design for the new facility to offer maximum exposure to traffic on Highway 75.
Rock Rapids, IA