Client:
Sioux Center Community Hospital & Health Center

Sioux Center, IA

Key Features:

  • New Hospital Facility
  • Heliport
  • Permanent Retention Pond & Stream Restoration
  • Mobile MRI Bay

Key Experience:

  • Project Coordination with architect, ownership group, general contractor and subcontractors
  • Communication with project stakeholders
  • Working with USDA Funded project

Hospital Site Development

Sioux Center Community Hospital relocated their hospital facility, which required the completion of several smaller projects in conjunction with the overall hospital construction project.

The new hospital facility design included City utility connections, accounting for the increased traffic on the local road system, mass excavation to accommodate the side hill construction and walk-out basement, a storm water study to analyze the adjacent natural drainage creek, a new helipad facility, a decorative garden overlooking the retention pond, as well as a mobile MRI parking bay. The facility opened in the spring of 2014.

Featured Projects

All
  • All
  • Aviation
  • Civil
  • Electrical Power
  • Survey
  • Wastewater
  • Water

Floodplain Analysis

DGR employed a Geographic Information System (GIS) in conjunction with the U.S. Army Corps of Engineers to first determine the 100-year flood elevations and delineate the floodway boundaries.

Floodplain Analysis
Sutherland, IA

Distribution Conversion

Due to concerns with the age and condition of the structures, along with safety clearances to energized equipment and conductors, a project was undertaken to replace the old infrastructure with new underground lines and associated padmount equipment.

Distribution Conversion
Redwood Falls, MN

Street & Utility Improvements

Morningside Avenue was reconstructed totaling approximately 1,300 linear feet. The project included new sanitary sewer, water main, storm sewer, fiber conduits, decorative street lighting, and 9-inch concrete paving with colored concrete sidewalks.

Street & Utility Improvements
Sioux City, IA

Wastewater Treatment Facility (SBR)

The City ultimately determined a flow-through style SBR system to be the preferred choice based on the selection criteria and the ability to meet anticipated permit limits.

Wastewater Treatment Facility (SBR)
Orange City, IA

Site Development

Planning started with site plan design for the new facility to offer maximum exposure to traffic on Highway 75.

Site Development
Rock Rapids, IA

Wastewater Treatment Facility (SBR)

The new plant, rated for 5.3 million gallons per day (MGD) peak day, doubles the capacity of its predecessor.

Wastewater Treatment Facility (SBR)
Sheldon, IA